Specifications include, but are not limited to: Final Yard Clean-Up in Disturbed Areas (SF) The area receiving “Seeding, Fertilizing and Mulching” shall be computed using the trapezoidal method with the horizontal dimensions measured to the nearest foot. The horizontal area of individual trapezoids shall be summed, converted to Square Feet, and rounded to the nearest 0.1 Square Foot for each pay application. This item will be paid for at the Contract unit price per Square Yard for “Seeding, Fertilizing and Mulching”. Completed sodding, measured as provided above, shall be paid for at the Contract unit price per Square Foot for “Sodding”. Said payment shall be full compensation for preparation of the ground, furnishing and planting all seed* and sods, fertilizing, compacting, watering, and staking, and for all labor tools, equipment and incidentals necessary to complete the work as specified. Section 4.19, Page 4-31 thru 4-37 *specific to this contract, seed mixture and suggested rates of application are listed below. The Contractor shall be responsible for adapting the seed mixture and rate of application to the site conditions so as to insure a uniform stand of healthy grass with a density of 70% coverage within 12 months from the date of project acceptance and in reasonable conformity with adjacent areas. Seed mixtures and rates, if different from those given herein, shall be approved by the Engineer.